For each of the photos below, click on the photo for a larger
version of the image.
 |
West Wall Elevation
This shows construction details, including the use of concrete block
walls grouted solid with 10-inch steel U-channel inverted on top and
held down with J-hooks in the walls. The crane rail upon which the roof
rolls is bolted to the channel using hooked bolts. |
 |
Cable Holes in the Walls
There are four PVC pipes embedded in holes in the walls -- in each
of the east and west building walls, there is one of these in each of
the shop walls and each of the observatory walls. These are for passing
cables through the concrete block of the walls, which contain rebar and
are grouted solid. To keep out insects, the holes are filled with
expanding spray foam from an aerosol can. When a new cable is added,
the old foam is cleaned out (a bit of a job, as it is quite sticky),
the new cable is passed through the PVC liner, and new foam is squirted
into the hole. |
 |
Shop Wall Counterforts
The first 10 feet of the 15-foot high shop wall is underground. To
withstand the consequent overturning moment of the dirt piled against
the walls, the structural engineer required counterforts every 64
inches -- piles of additional blocks with four vertical #5 rebars tied
every other course around two vertical bars in the walls with a #3
horizontal bar looped through around all six bars. Each wall has a
horizontal #5 bar in every other course in bond beam, plus a vertical
#5 bar every 24 inches. |
 |
Shop Rainwater Scupper Downspouts
The shop roof is suspended between parapet walls, that is, the walls
are higher than the roof, to permit the observatory roof to roll
unimpeded over the shop roof. The roof slopes one block course (8 inches)
from east to west (the side shown in this photo) so that rain water
flows westward. Crickets built into the roof channel the water towards
four scuppers through the wall into these downspouts. The downspouts
empty into a concrete bed that moves the water into a small cistern
and into a 4-inch pipe that drains downhill away from the house and
observatory. |
 |
Top Wall Cooling Pipes
Cooling pipes are embedded along the top of the enire east and
west walls of the building, including both the shop and observatory.
This was done at the time of construction without knowing if they
would ever be needed. They are ordinary black steel pipe embedded in
the concrete block before it was grouted, with a pipe going in,
running along the block, and exiting 8 feet later (8 feet was chosen
as it was an integer multiple of the 16-inch length of the block size).
The outside of the walls will be insulated with 4 inches of rigid foam,
then covered with corrugated sheet steel of the type used on the roof. |
 |
Individual Pier Cooling Pipes
Each of the six major piers is encircled by a cooling pipe
embedded in the concrete slab. The pipes enter and leave the slab
at the nearest exterior wall. As of this time, just as with the
wall cooling pipes, there is no water chiller and the pipes are
not connected to anything. They had to be installed at the time of
building construction before the concrete was poured -- adding them
later would have been too disruptive, in terms of jack-hammering
concrete and creating too much dust while we were trying to observe.
So far, we have not seen the need to purchase a chiller and cool the
walls or slab. |
 |
Exterior Wall Insulation Installation
During the summer of 2002, Winer used a local contractor to
install six inches of polyurethane foam insulation on the east,
west, and south exterior walls of the shop and observatory. The
north wall of the building, which is the north wall of the shop
furthest from the observatory facing the house, is coated with
stucco to match the nearby house. This insulation not only makes
the shop easy to work in during summer and winter, and reduces
heating and cooling costs, it should improve seeing in the
observatory by reducing the heating of the thermally massive
walls of the observatory. |
 |
Finished Exterior Observatory Walls
After installation of the polyurethane foam during the summer
of 2002 (see above), the installed foam was covered by wood
firring strips, then 29 gauge corrugated sheet metal was placed
over the firring strips, which keep the sheet metal (heated by
the sun) off the foam, and provide a layer of air that also
provides some insulation. |
Last modified: January 1, 2008.